TxDOT provides update on the Navarro median project

VICTORIA, Texas- A press release from Teas Department of Transportation provides an update on the Navarro media project.

The Contractor has been working on Rio Grande installing sidewalks and curb ramps at the northern corners of Hospital Dr. and Palm Dr.

Work will begin on the sidewalks and driveways between Palm Dr. and Oleander Dr. starting Monday July 13th.

On the week of July 13th through July 17th the Contractor will begin pavement milling from Loop 463 south toward Huvar St.

The Subcontractor will begin boring for new illumination poles from Loop 463 south.

Beginning July 20th, 2020 long term lane closure will be installed beginning at Loop 463 and continue to Huvar St. The inside lanes in each direction will be closed for approximately one month while the contractor installs the new concrete median.

Click here to read more about the project.