Construction on Crestwood Continues

Another Victoria area roadway seeing construction work is Crestwood drive.

Ken Gill, engineer with the city of Victoria, says that Crestwood in undergoing a complete redo, complete with resurfacing, new water and sewer lines, and new sidewalks. Gill says so far the project remains on track, with only a few setbacks.

“Some of the issues we ran into, some underground utilities that went unmarked on the plans we didn’t know the depths, but we are going to work around that, and there are certain blocks of Crestwood that we may have to close for a day, to set those gas lines and utilities across there safely,” said Gill.

Gill says that the expected completion date for the entire re-do of Crestwood drive from Navarro to Ben Jordan is by spring of 2021