City provides update on Navarro median project

VICTORIA, Texas — Navarro Median Project Update:

Rio Grande St.: Contractor has been working on Rio Grande installing sidewalks and curb ramps at the northern corners of Hospital Dr. and Palm Dr.. Contractor will begin working on sidewalks and driveways between Palm Dr. and Oleander Dr. starting Monday July 13th.

Navarro Work: Week of July 13th through July 17th: Contractor will begin pavement milling from Loop 463 south toward Huvar St.. Subcontractor will begin boring for new illumination poles from Loop 463 south.

Beginning July 20th, 2020: Long term lane closure will be installed beginning at Loop 463 and continue to Huvar St.. The inside lanes in each direction will be closed for approximately one month while the contractor installs the new concrete median.

For media inquiries you can contact Lucea’n Kuykendall- Herring with the Public Information Office at 361-293-4436.

 

Courtesy: City of Victoria